NORDIC PROCUREMENT ENFORCEMENT
  LEGAL RESEARCH PROJECT
   

   
 
 
 
    
 
 
Previous
Up
   
   
c3-63
c3-64
c3-65

32004L0018: c3-65

Time limit for the receipt of requests to participate and receipt of tenders

EU Law Community DK Law EU Cases DK Cases

EU Law

32004L0018 - Classic (3rd generation) Article 65
Article 65
    Time limit for the receipt of requests to participate and receipt of tenders
    In works contracts awarded by a works concessionaire which is not a contracting authority, the time limit for the receipt of requests to participate, fixed by the concessionaire, shall be not less than 37 days from the date on which the contract notice was dispatched and the time limit for the receipt of tenders not less than 40 days from the date on which the contract notice or the invitation to tender was dispatched.
    Article 38(5), (6) and (7) shall apply.
31993L0037 - Works (2nd generation) Article 16
Article 16
    In works contracts awarded by a works concessionnaire other than a contracting authority, the time limit for the receipt of requests to participate, fixed by the concessionnaire, shall be not less than 37 days from the date of dispatch of the notice, and the time limit for the receipt of tenders not less than 40 days from the date of dispatch of the notice or the invitation to tender.
31989L0440 - Fourth amendment of Works (1st generation) Article 1.13=W1-15b
Article 15b
    In works contracts awarded by a concessionaire of works other than an authority awarding contracts, the time limit for the receipt of requests to participate shall be fixed by the concessionaire at not less than 37 days from the date of dispatch of the notice, and the time limit for the receipt of tenders at not less than 40 days from the date of dispatch of the notice or the invitation to tender.

EU Cases

Case PteRefText