C-44/96 Mannesmann | 47-49 | W2-1.b.1 S2-41 [implicit] RC1A1-1.1 R93.2081-7.1 | 47 By its seventh question, the national court is essentially seeking to ascertain whether Article 7(1) of Regulation No 2052/88 as amended by Regulation No 2081/93 is to be interpreted as meaning that Community funding of a works project is conditional upon the recipients complying with the review procedures laid down by Directive 89/665, even if they themselves are not contracting authorities within the meaning of Article 1(b) of Directive 93/37. 48 As the Advocate General noted at point 105 of his Opinion, it is clear from the wording of Article 7(1) of Regulation No 2052/88 that the requirement that the measures referred to must be in conformity with Community law presupposes that those measures fall within the scope of the relevant Community legislation. 49 The answer to the seventh question referred by the national court must therefore be that Article 7(1) of Regulation No 2052/88 as amended by Regulation No 2081/93 is to be interpreted as meaning that Community funding of a works project is not conditional upon the recipients complying with the review procedures within the meaning of Directive 89/665, if they are not themselves contracting authorities within the meaning of Article 1(b) of Directive 93/37. |